Renovation Corner

District Improvements

UPCOMING

  • New fence will be in installed in the next few weeks.
  • School Exterior Sign will be installed this week
  • Bathrooms are mostly complete
  • Millwork (storage cabinets) in classrooms is in progress

COMPLETED

  • Sidewalks replaced around the campus, some re-leveling
  • Plumbing and Clean-up around the site
  • Fence removal

 

    PTO Improvements

    UPCOMING

    • Install shade sails over outdoor classroom
    • 4-H Garden installation
    • Replicating the Mayflower mural to jazz up the drop-off area on the Nairn side of the school
    • Landscaping front of school coming this fall

    COMPLETED

    • Outdoor classroom: Huge shoutout to Me-Moes Lawn & Landscaping who removed trees and shrubs prior to the work day to save us time and effort. The rest of the classroom work was:
      1. Fence removal
      2. Gravel surfacing
      3. Grading surface
    • Front of school
      1. Striped Parking Lot
      2. Primed planters & steps
      3. Mulched under trees, in beds
    • 2nd Floor Storage
      1. Cleaned area
      2. Installed Shelving
    • Garden
      1. Moved and installed Garden Shed
    Claire PittmanComment